Installing a ground mount solar system offers property owners unmatched flexibility and energy yield, but the process requires careful planning and technical expertise. Whether for a residential, commercial, or utility-scale project, this step-by-step guide breaks down the installation journey—from site assessment to final commissioning—with a focus on optimizing efficiency using Yijia Solar’s innovative racking and tracking solutions.
Step 1: Pre-Installation Planning and Site Assessment
1.1 Define Your Energy Goals
· Calculate annual energy consumption to determine system size (e.g., a 10kW system offsets ~12,000 kWh/year for an average home).
· Yijia Solar’s free energy calculator helps size systems based on location and usage patterns.
1.2 Site Analysis Essentials
· Sunlight Exposure: Use PVWatts to ensure 6–8 hours of direct sunlight daily. Avoid north-facing slopes (Northern Hemisphere) and shaded areas.
· Soil Type:
· Sandy/loamy soil: Ideal for helical piles (install in 15 minutes/pile).
· Clay/rocky soil: Concrete footings may be necessary, increasing installation time by 60%.
· Yijia Solar Advantage: Free 3D site modeling to optimize panel placement and shade mitigation.
Step 2: Foundation Installation for Long-Term Stability
2.1 Helical Pile Foundations (Ideal for Most Soils)
Pile Selection:
· Yijia Solar’s galvanized steel helical piles (80μm zinc coating) support 2,000+ lbs and pass 1,000+ hours of salt spray testing.
. Installation Process:
· Use a hydraulic pile driver to screw piles into the ground until reaching load-bearing strata (typically 3–5 feet deep).
· Leveling brackets ensure precise height adjustment (±0.5°).
2.2 Concrete Footing Foundations (For Heavy-Duty Projects)
. Excavation: Dig 2–3 foot deep holes for footings, spaced according to racking design.
. Reinforcement and Pouring:
· Insert steel rebar cages, then pour concrete (minimum 3,000 psi strength).
· Cure for 7–10 days before installing racks.
Step 3: Racking System Installation
3.1 Galvanized Steel vs. Aluminum Racks
· Galvanized Steel:
· Q235 hot-dip galvanized steel racks withstand 140 mph winds and 60 psf snow loads, ideal for utility-scale projects.
· Aluminum Racks:
· 6005-T5 aluminum reduces weight by 30%, perfect for residential or commercial installations.
3.2 Yijia Solar’s SnapLock™ Racking Technology
1. Rail Installation:
· Lay main rails across foundations, securing with pre-punched holes and stainless steel fasteners.
· Yijia Solar’s SnapLock™ rails reduce installation time by 40% with self-aligning connectors.
1. Crossbar Placement:
· Attach crossbars at 1–1.5m intervals to support panel weight evenly.
Step 4: Solar Panel Installation and Wiring
4.1 Panel Mounting Best Practices
. Panel Alignment:
· Position panels with 20–40° tilt (Northern Hemisphere) for maximum sunlight capture.
· Yijia Solar’s adjustable tilt brackets enable seasonal angle adjustments (e.g., 30° in summer, 40° in winter).
. Electrical Connections:
· Use MC4 connectors to link panels in series, routing cables through weatherproof conduit.
4.2 Tracking System Integration (Optional)
· Single-Axis Tracker Installation:
. Mount tracker motors on main rails, connecting to control units.
. Yijia Solar’s SmartTrack™ system features ±0.1° accuracy, increasing yield by 25%.
· Wiring Integration:
· Connect tracker motors to the inverter for synchronized operation.
Step 5: Inverter Setup and Grid Connection
5.1 Inverter Placement
· Install string or microinverters in a shaded, ventilated area (e.g., utility shed), within 50 feet of the array for minimal power loss.
5.2 Electrical Panel Upgrades
· Upgrade the main electrical panel to accommodate solar power, installing a bidirectional meter for net metering.
5.3 Permitting and Inspections
· Submit installation plans to local authorities for permits, scheduling inspections for:
· Foundation stability
· Electrical wiring compliance
· Wind/snow load calculations (Yijia Solar provides certified engineering reports).
Step 6: System Commissioning and Monitoring
6.1 Performance Testing
· Use a multimeter to verify DC voltage output, then power on the inverter to check AC conversion.
· Yijia Solar’s cloud-based monitoring platform enables real-time performance tracking.
6.2 Maintenance Planning
· Schedule annual inspections for:
· Loose fasteners or corroded components
· Tracker motor lubrication (if applicable)
· Panel cleaning (recommended 2–3 times/year in dusty areas).
Cost-Saving Installation Tips from Yijia Solar
1.Modular Design: Start with a 5kW system and expand later, leveraging Yijia Solar’s scalable racking.
2. Helical Piles: Save 30% on foundation costs vs. concrete footings, especially for sandy soil.
3. Bulk Pricing: Projects over 100kW qualify for discounted racks and panels.
Why Choose Yijia Solar for Installation
1. Technical Expertise
· 25+ Patents: Including the Single Column Support System (reduces material use by 25%) and SnapLock™ technology.
· Certified Installers: Trained crews with 10,000+ projects completed worldwide.
2. Comprehensive Services
· Turnkey Solutions: From design to O&M, with 24/7 technical support.
· Warranty Coverage: 15-year rack warranties and 25-year panel performance guarantees.
Take the Next Step with Yijia Solar
Ready to install your ground mount solar system? Yijia Solar’s experts offer:
· Free Site Assessment: Soil testing, 3D modeling, and cost projections.
· Custom Design Plans: Tailored to your terrain, energy goals, and budget.
· Financing Options: Leasing, PPAs, and tax credit assistance.
Contact Yijia Solar Today to schedule a consultation and receive a detailed installation quote. Maximize your solar investment with a partner who combines technical excellence with installation efficiency.
Latest News
Product Display
YiJia Solar focuses on the production of solar photovoltaic support systems, providing one-stop smart energy solutions and a full range of home energy storage configurations.